      An optimization model to solve the resource constrained project scheduling problem RCPSP in new product development projects Translated title: Un modelo de optimización para resolver el problema de programación de proyectos con recursos restringidos RCPSP en proyectos de desarrollo de nuevos productos

      research-article

      Read this article at

      Bookmark
          There is no author summary for this article yet. Authors can add summaries to their articles on ScienceOpen to make them more accessible to a non-specialist audience.

          Abstract

          Abstract New product development projects (NPDP) face different risks that may affect the scheduling. In this article, the purpose was to develop an optimization model to solve the RCPSP in NPDP and obtain a robust baseline for the project. The proposed model includes three stages: the identification of the project’s risks, an estimation of activities’ duration, and the resolution of an integer linear program. Two versions of the model were designed and compared in order to select the best one. The first version uses a method to estimate the activities’ duration based on the expected value of the impact of the risks and the second version uses a method based on the judgmental risk analysis process. Finally, the two version of the model were applied to a case study and the best version of the model was identified using a robustness indicator that analyses the start times of the baselines generated.

          Translated abstract

          Resumen Los proyectos de desarrollo de nuevos productos (PDNP) enfrentan riesgos que afectan su programación. En este artículo, el propósito fue desarrollar un modelo de optimización para resolver el RCPSP en PDNP y obtener una línea-base robusta para el proyecto. El modelo propuesto incluye tres etapas: identificación de riesgos, estimación de la duración de las actividades y resolución de un programa lineal entero. Dos versiones del modelo fueron creadas con el fin de compararlas y seleccionar la mejor versión. La primera versión utiliza un método para estimar la duración de las actividades basado en el valor esperado del impacto de los riesgos, y la segunda, un método basado en el proceso de análisis de riesgos críticos. Finalmente, las dos versiones del modelo fueron aplicadas a un caso de estudio y la mejor versión fue identificada empleando un indicador de robustez que analiza los tiempos de inicio de las líneas-base generadas.

          Related collections

          Most cited references30

          • Record: found
          • Abstract: not found
          • Article: not found

          The use of buffers in project management: The trade-off between stability and makespan

            Bookmark
            • Record: found
            • Abstract: not found
            • Article: not found

            A Knowledge-Based Evolutionary Multiobjective Approach for Stochastic Extended Resource Investment Project Scheduling Problems

              Bookmark
              • Record: found
              • Abstract: not found
              • Article: not found

              An investigation of buffer sizing techniques in critical chain scheduling

                Bookmark

                Author and article information

                Journal
                dyna
                DYNA
                Dyna rev.fac.nac.minas
                Universidad Nacional de Colombia (Medellín, Antioquia, Colombia )
                0012-7353
                2346-2183
                March 2020
                : 87
                : 212
                : 179-188
                Affiliations
                [2] Medellín orgnameUniversidad Nacional de Colombia orgdiv1Facultad de Minas Colombia javidiaz@ 123456unal.edu.co
                [1] Bucaramanga Santander orgnameUniversidad Industrial de Santander orgdiv1Escuela de Estudios Industriales y Empresariales Colombia nortiz@ 123456uis.edu.co
                Article
                S0012-73532020000100179 S0012-7353(20)08721200179
                10.15446/dyna.v87n212.81269
                59fd1933-4e67-4ba1-8120-0635b8258db1

                This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.

                History
                : 11 February 2020
                : 23 July 2019
                Page count
                Figures: 0, Tables: 0, Equations: 0, References: 48, Pages: 10
                Product

                SciELO Colombia

                Categories
                Articles

                new product development,duración aleatoria,project scheduling,robustez,baseline,riesgos,línea-base,desarrollo de nuevos productos,programación de proyectos,robustness,random duration,risks

                Comments

                Comment on this article