      Metodología de toma de decisiones para la selección de subcontratos en la industria de la construcción Translated title: Methodology of decision-making for the selection of subcontracts in the construction industry

      research-article

      Read this article at

      Bookmark
          There is no author summary for this article yet. Authors can add summaries to their articles on ScienceOpen to make them more accessible to a non-specialist audience.

          Abstract

          Una selección de subcontratistas errónea en la industria de la construcción causa problemas críticos como: retrasos en los proyectos, calidad deficiente de los trabajos y costos adicionales. Este trabajo entrega una herramienta para la selección de subcontratos, ésta se traduce en una metodología de toma de decisiones para seleccionar el subcontrato más adecuado para cada proyecto. Para lograr el objetivo, primero se determinan las prácticas actuales de subcontratación a través de una encuesta que fue contestada por cincuenta empresas del rubro. Posteriormente, se analizan dos métodos de toma de decisiones (WRC y CBA) en una simulación de toma de decisiones que fue realizada a diez empresas del rubro de forma presencial. Los resultados fueron concluyentes, en doce de las quince simulaciones el método WRC destacó al contrastarse con el método CBA, por lo cual se define al método WRC como el más adecuado para este tipo de selección. Finalmente, se presenta la metodología de toma de decisiones como una herramienta de optimización del proceso de selección de subcontratistas, en ésta se incluyen aspectos como: recomendaciones antes del proceso de selección y la estructura en detalle para desarrollar correctamente el método WRC.

          Translated abstract

          A poor selection of subcontractors in the construction industry causes critical problems such as: delays in projects, poor quality of work and additional costs. This paper provides a tool for selection of subcontracts, which translates into a decision-making methodology to select the most suitable subcontract for each project. To achieve this objective, first the current subcontracting practices are determined through a survey that was answered by fifty companies of the sector. Subsequently, the decisionmaking methods (WRC and CBA) are analyzed in a decision-making simulation that was carried out to ten companies in the field. The results were conclusive, in twelve of the fifteen simulations, WRC method highlighted when contrasting with the CBA method, so the WRC method is defined as the most appropriate for this type of selection. Finally, the decision-making methodology is presented as an optimization tool for the selection process of subcontractors, which includes aspects such as: recommendations before the selection process and structure in detail to correctly develop the WRC method.

          Related collections

          Most cited references10

          • Record: found
          • Abstract: not found
          • Article: not found

          Causes of delay in large construction projects

            Bookmark
            • Record: found
            • Abstract: not found
            • Article: not found

            Causes and effects of delays in Malaysian construction industry

              Bookmark
              • Record: found
              • Abstract: not found
              • Article: not found

              Causes of construction delay: traditional contracts

                Bookmark

                Author and article information

                Contributors
                Role: ND
                Role: ND
                Journal
                oyp
                Obras y proyectos
                Obras y Proyectos
                Universidad Católica de la Santísima Concepción (Concepción, , Chile )
                0718-2813
                December 2018
                : 0
                : 24
                : 28-40
                Affiliations
                [1] Valparaíso Valparaíso orgnamePontificia Universidad Católica de Valparaíso orgdiv1Facultad de Ingeniería orgdiv2Escuela de Ingeniería Civil Chile andrescrisostomoriquelme@ 123456gmail.com
                Article
                S0718-28132018000200028
                10.4067/s0718-28132018000200028
                f336b5b9-ed35-4975-900d-eb8418101689

                This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

                History
                : 19 March 2018
                : 17 October 2018
                Page count
                Figures: 0, Tables: 0, Equations: 0, References: 20, Pages: 13
                Product

                SciELO Chile

                Categories
                Artículos

                subcontratación,industria de la construcción,toma de decisiones,WRC,CBA,subcontracts,construction industry,decision-making

                Comments

                Comment on this article