      TEACHING HOW TO USE A REPETITIVE SCHEDULING METHOD WHEN PLANNING A GREEN CONDOMINIUM BUILDING

      research-article

      Read this article at

      ScienceOpenPublisher
          There is no author summary for this article yet. Authors can add summaries to their articles on ScienceOpen to make them more accessible to a non-specialist audience.

          Abstract

          This paper aims to present a methodology for use in construction planning named the Repetitive Scheduling Method (RSM). Students on a graduate level construction management program can learn how to create a RSM schedule to be applied to a real project. Typically, the Critical Path Method (CPM) is used to plan general construction projects. This paper presents a case study wherein a CPM diagram is transformed into a RSM schedule for use in the construction of a green condominium. RSM is the most suitable tool for planning repetitive projects like condominium buildings, apartment complexes, or real estate development projects. It utilizes an uninterrupted flow of resource concept in order to eliminate manpower-related resource wastage. As a result, construction productivity can be improved by using the right construction planning tool on the right project. Interested graduate students researching construction engineering can apply RSM on their repetitive projects in the future.

          Related collections

          Most cited references7

          • Record: found
          • Abstract: not found
          • Article: not found

          Scheduling Projects with Repeating Activities

            Bookmark
            • Record: found
            • Abstract: not found
            • Article: not found

            Line‐of‐Balance Scheduling in Pavement Construction

              Bookmark
              • Record: found
              • Abstract: not found
              • Article: not found

              Repetitive scheduling method: Requirements, modeling, and implementation

                Bookmark

                Author and article information

                Journal
                jgrb
                Journal of Green Building
                College Publishing
                1552-6100
                1943-4618
                1943-4618
                Spring 2019
                : 14
                : 2
                : 203-217
                Author notes

                1. Associate Professor, King Mongkut's University of Technology North Bangkok, Department of Civil Engineering, 1518 Pracharad 1 Rd., Bangsue, Bangkok, 10800, Thailand, wannawit@ 123456gmail.com

                *Corresponding Author

                2. Lecturer, Sukhothai Thammathirat Open University, School of Management Science, Chaengwattana Rd., Pakkret, Nonthaburi, 11120, Thailand, nattasit.chaisaard@ 123456gmail.com

                Article
                jgb.14.2.203
                10.3992/1943-4618.14.2.203
                8bbcd12d-aae5-453e-9dd9-8c64fb794c96
                © 2019 College Publishing
                History
                Page count
                Pages: 15
                Categories
                NEW DIRECTIONS IN TEACHING AND RESEARCH

                Urban design & Planning,Civil engineering,Environmental management, Policy & Planning,Architecture,Environmental engineering
                Scheduling,Writing RSM,Teaching,Repetitive Scheduling Method,Planning

                Comments

                Comment on this article