27
views
0
recommends
+1 Recommend
0 collections
    0
    shares
      • Record: found
      • Abstract: found
      • Article: found
      Is Open Access

      Applying lean improvement methodology within a public health context: administration and organisation of a training programme

      research-article

      Read this article at

      Bookmark
          There is no author summary for this article yet. Authors can add summaries to their articles on ScienceOpen to make them more accessible to a non-specialist audience.

          Abstract

          Problem The Health Improvement team, housed within the Public Health Department of National Health Service (NHS) Highland, deliver key objectives around health improvement, tackling health inequalities and building capacity. The processes surrounding the delivery of the building capacity objective had been built up over a period of time and historically were administered by different staff members. This led to different ways of organising training and no overall agreed approach. The impact of a non-standard approach meant that it was often difficult to get an overview of what was being delivered and who was attending the various training offered. Furthermore, there were duplicate processes in place that were person dependent that could be done in a more effective way. Our overall aim for the project was to introduce a standard approach to how training was organised and a way of ensuring that data could be collected and reviewed instantly so that we could report out on a monthly basis.1 Method We began by applying a tool called process mapping,2 which sets out the steps that take place within any specific function. The particular function that we looked at was organising and booking the health improvement motivation interviewing training. Once the map was completed, it is then interrogated in order to understand why some of the steps were required and whether there is any duplication (non-value-added waste). See figure 1. Figure 1 Current state administrative training processes. BHC, behaviour change; MI, motivational interviewing; NHSH, National Health Service Highland. Following on from this, we mapped out what a desired process or future state might look like and developed standard work.3 We tested out the standard work with two members of staff initially and amended accordingly before applying it further. See figure 2. Figure 2 Future state training administration—flowchart. HPD, Health Promotion Department. We also tested out using a PDSA (Plan, Do, Study, Act) cycle the introduction of a standard evaluation tool in order to compare results across different training courses delivered. By carrying out observations, it was apparent that staff were recording information in different ways which resulted in duplication of work. To improve the process, we developed a database which set out agreed steps for all administration staff about how a course should be managed. The database records all the information in one place and enables instant reporting of numbers of attendees, role and location of courses. The success of the training programme is underpinned by access to and use of training resources. Observations showed that staff had developed their own resources, and these were often housed in different places making it difficult to locate the desired items. Furthermore, this led to poor stock control. We used a lean tool called 5S,4 which consists of five different stages in ensuring resources are effectively managed. The five steps consist of sort, simplify, sweep, standardise and self-discipline. The photographs below illustrate an example of how the resources were managed before we began the process and the results after we applied 5S. See figures 3 and 4. Figure 3 Before the 5S process was applied. Figure 4 After the 5S process was applied. Stock control was improved for three standard training packs by introducing a kanban inventory control system of cards that outlined the information needed when re-ordering items. This has resulted in timely restocking and less waste as we now only order items needed. Results We collected measurements (table 1) before we applied the lean tools that demonstrated it took between 4 and 5 days to find the information and then produce a training activity report. With the new capacity of the database, a report can be generated in minutes. We estimated that we were able to reduce the length of time taken in organising a course from 2 hours to 1 hour. This allowed the team to reallocate the time saved in administration to other health improvement programmes. The staff delivering training and staff involved in the administration were often being asked to organise training at the last minute resulting in additional pressure. By introducing a standard operating procedure (SOP), which included the minimum notice required for staff, this was breached on one occasion only within the test period. Table 1 Metrics training programme Intermediate lean training Improvement project measurement Title: Applying Improvement Methodology within a Public Health Context Date of reporting: 26 May 2017 Report by: team leaders Change against baseline PDSA cycles Baseline Cycle 1 Cycle 2 Length of time to collate training data 4–5 days 30 min 30 min 98.3% reduction (4 days) Generate report for Motivational Interviewing course 1 day 10 min 4 min 99.1% reduction Training requests sent to administration 10 weeks in advance of training taking place 50%–60% of courses requested less than 10 weeks’ notice 90% compliance within first month of testing 90% compliance within first month of testing 40%–60% increase Reduction in length of time taken in organising training 2 hours administration time per course 1 hour 30 min 1 hour 50% reduction 5S audit 1 2 4 – PDSA, Plan, Do, Study, Act. Other metrics, showing an improvement, included training requests being 10 weeks in advance of the start date and a reduction in length of time spent in organising the training. The 5S audit was also included in the metric sheet. Conclusions Lean is about identifying value-added activity and non value activity in systems and ensuring that in eliminating the waste, we can operate in a much more efficient manner. The application of lean within a Public Health context was less well known; however, this project demonstrates that lean can be as easily applied to processes within public health as to a clinical setting. Furthermore, given the pressures on NHS budgets it is vital that Health Improvement programmes are run as efficiently as possible. We estimated that by introducing these improvement tools, we saved 25% of each hour spent on the training administration at a cost of £9.38 per hour (Agenda for Change), which was then reallocated to support other work. The introduction of a SOP is key to sustaining this work. The next steps are to apply our learning in larger-scale pieces of health improvement work.

          Related collections

          Author and article information

          Journal
          BMJ Open Qual
          BMJ Open Qual
          bmjqir
          bmjoq
          BMJ Open Quality
          BMJ Publishing Group (BMA House, Tavistock Square, London, WC1H 9JR )
          2399-6641
          2018
          3 September 2018
          : 7
          : 3
          : e000257
          Affiliations
          [1]departmentDepartment of Public Health , NHS Highland , Inverness, UK
          Author notes
          [Correspondence to ] Elisabeth Smart; elisabeth.smart@ 123456nhs.net
          Article
          bmjoq-2017-000257
          10.1136/bmjoq-2017-000257
          6135472
          6f73c5b3-7dcc-4ace-8367-0a0f9ca990ef
          © Author(s) (or their employer(s)) 2018. Re-use permitted under CC BY-NC. No commercial re-use. See rights and permissions. Published by BMJ.

          This is an open access article distributed in accordance with the Creative Commons Attribution Non Commercial (CC BY-NC 4.0) license, which permits others to distribute, remix, adapt, build upon this work non-commercially, and license their derivative works on different terms, provided the original work is properly cited, appropriate credit is given, any changes made indicated, and the use is non-commercial. See: http://creativecommons.org/licenses/by-nc/4.0/.

          History
          : 17 November 2017
          : 31 July 2018
          : 11 August 2018
          Categories
          Short Report
          1506
          Custom metadata
          unlocked

          lean management,pdsa,quality improvement methodologies,continuous quality improvement

          Comments

          Comment on this article